1977-78: First construction project completed to start the Rural Water District.
1997: 50,000 gallons elevated tank constructed.
1997: Highway 13 construction project.
1997: 2 wells developed and put into service.
1997: Well Pump Station constructed.
1997: Olsburg Booster Pump Station constructed.
1997: 24,500 gallon ground storage tank constructed.
2006: Spring Creek construction project.
2006-07: 190,000 gallon standpipe constructed.
2009: Installation of new SCADA control system.
2013: New VFD's and electrical component upgrade at Well Pump Station.
2019: Installed new remote meter reading system.
2022: Installed new gas chlorination system.
Facts & Figures (2022):
Provide Water Service To (2022):